E2: $8 Billion and 16 New Clean Energy Projects
Since federal clean energy tax credits were passed by Congress in August 2022, a total of 34 projects have been cancelled,
Since federal clean energy tax credits were passed by Congress in August 2022, a total of 34 projects have been cancelled,
– A California lawmaker is calling for an end to the Morro Bay battery energy project following a fire at a lithium battery storage facility in Moss Landing, operated by Texas
Five projects — or the equivalent of $6.7 billion of lost investment — were downsized or cancelled in June alone, all of them in the electric vehicle or battery storage
The Trump administration on Monday ordered a halt to five offshore wind projects currently being built in the United States, a major new attack on a power-generating industry
Energy Secretary Chris Wright said Friday he canceled nearly $4 billion in project grants, in another massive blow to clean energy and greenhouse gas emissions reduction
Clean energy manufacturers canceled, closed or downsized nearly $8 billion in projects in the first quarter of 2025, as the Trump administration''s rollback of support for the
Energy Secretary Chris Wright said Friday he canceled nearly $4 billion in project grants, in another massive blow to clean energy and
Since federal clean energy tax credits were passed by Congress in August 2022, a total of 34 projects have been cancelled, closed or downsized, according to data from E2 and
Five projects — or the equivalent of $6.7 billion of lost investment — were downsized or cancelled in June alone, all of them in
Over 20 GWh of planned energy storage cell capacity for 2028 have been cancelled so far this year, according to the Q2 2025 reports on energy storage supply,
Work on all five offshore wind projects along the Atlantic coast has again been halted.
The Trump administration this week escalated its efforts against renewable energy when it announced the cancellation of $7.56 billion in funding for projects in 16 states,
The Trump administration on Monday said it would pause leases for five wind farms under construction off the east coast, essentially gutting the country''s nascent offshore wind
The Trump administration this week escalated its efforts against renewable energy when it announced the cancellation of $7.56 billion in
Clean energy manufacturers canceled, closed or downsized nearly $8 billion in projects in the first quarter of 2025, as the Trump
PDF version includes complete article with source references. Suitable for printing and offline reading.
He noted that all five projects halted on Monday had undergone rigorous reviews, including by the Defense Department. “Ironically, these projects will actually benefit our national security by diversifying America’s energy supplies, providing much-needed reliable power for the grid and helping our economy,” Mr. Lippold said.
The electric vehicle and battery storage spaces have been particularly hard-hit, with 11 and 16 projects affected, respectively. Five projects — or the equivalent of $6.7 billion of lost investment — were downsized or cancelled in June alone, all of them in the electric vehicle or battery storage manufacturing space.
The Interior Department announced it is pausing all leases for large-scale offshore wind projects that are currently under construction, effective immediately. It lands as the Trump administration is facing political heat from skyrocketing energy costs in part from the growth of data centers and artificial intelligence.
Trump administration orders halt to offshore wind projects. What it means. The Trump administration has ordered a halt to all work on five offshore wind farms along the Atlantic coast. Interior Secretary Doug Burgum cited national security risks, including radar interference, as the reason for the pause.